The idea actions are only flagged as yellow (amber) if their due date is within the next 14 days. This setting can be changed by going to Admin > Settings and changing the "Amber Status Due Date Threshold" setting under the Ideas section.


Below are the rules for how the actions are flagged:

  • Blue: Action is incomplete, and the due date is after the Amber Status due date threshold
  • Amber: Action is incomplete, and the due date is less than or equal to the Amber Status due date threshold
  • Red: Action is incomplete, and the due date is in the past
  • Green: Action is completed


Please note that the current pipeline will only show the counts for Amber and Red actions.