A constant node will have the same value for baseline, target and actual. All fixed over time.
If you change any value in a variable or constant node at any point, that change will impact historical outputs as well.
You will need to use an input KPI whenever the value changes over time. This obviously relates to things such as tonnes produced, but also if you have another value like number of drill rigs that you want to change month to month.
What is the difference between Constant and KPI node in a VDT?
Modified on: Fri, 21 Sep, 2018 at 12:59 PM
Did you find it helpful? Yes No
Send feedbackSorry we couldn't be helpful. Help us improve this article with your feedback.